Project Libre AI » All Posts https://projectlibre.com/forum/discussions/projectlibre-edu-training-and-consulting/feed/ Thu, 14 May 2026 17:09:04 +0000 https://bbpress.org/?v=2.6.14 en-US https://projectlibre.com/topic/evm-2/#post-6434 <![CDATA[Reply To: EVM]]> https://projectlibre.com/topic/evm-2/#post-6434 Mon, 08 Dec 2025 15:01:55 +0000 giamma C I thaks a lot for your answer.

I have reproduced the scenario following your advice: I set the Earned Value Method to “Physical Percent Complete” in the Advanced tab.

However, when I tried to update the progress, I noticed that the “Physical % Complete” field is read-only and cannot be edited directly.
Therefore, I had to update the standard “% Complete” field, which automatically updated the “Physical % Complete” to the same value.
Even in this scenario, with the Advanced setting applied, the problem persists: the Actual Cost is still recalculated based on the percentage, incorrectly showing 100 instead of 1,000.

What did I do wrong? Is there a specific step I am missing to decouple the input of actual hours worked from the physical progress?

]]>
https://projectlibre.com/topic/evm-2/#post-6431 <![CDATA[Reply To: EVM]]> https://projectlibre.com/topic/evm-2/#post-6431 Mon, 08 Dec 2025 13:06:18 +0000 Project_Libre Great question and there is an option in the Task detail dialog box. In the Advanced tab you can select if Earned Value Method is based on Percent Complete or Physical Percent Complete.

]]>
https://projectlibre.com/topic/evm-2/#post-6389 <![CDATA[EVM]]> https://projectlibre.com/topic/evm-2/#post-6389 Sat, 06 Dec 2025 23:16:43 +0000 giamma C Hello ProjectLibre team,
I would like to report a limitation I found regarding the update of Actual Costs (ACWP) when a task is performing inefficiently.

The Scenario:
I have a task with the following baseline:
Duration: 10 Days
BCWS (Budget): 1,000 (e.g., 1 resource @ 100/day)

The Reality:
The 10 days have passed. The resource has worked for the full 10 days (so I have paid the full 1,000), but they have encountered issues and only achieved 10% of the physical work.

The Problem:
If I update the % Complete to 10%, ProjectLibre automatically recalculates the Actual Cost down to 100 (assuming only 1 day of Actual Duration). This is incorrect because I have actually incurred the full cost of 1,000.
I cannot manually edit the Actual Cost cell to correct this figure to 1,000 because the field is read-only when resources are assigned.

The Consequence:
My Earned Value analysis is wrong. The software hides the cost overrun.
Current (Wrong) Result: ACWP = 100, BCWP = 100. Cost Variance = 0.
Expected (Correct) Result: ACWP = 1,000, BCWP = 100. Cost Variance = -900.

My Question:
Is there a way to decouple “Actual Work/Cost” from “% Complete”? How can I input that a resource has worked/consumed 100% of the budgeted hours while the task progress remains at only 10%, without having to use workarounds like “Fixed Costs”?
Thank you for your support.

]]>
https://projectlibre.com/topic/how-to-change-the-setup-from-week-to-month-in-gantt-chart/#post-3695 <![CDATA[Reply To: How to change the setup from Week to Month in Gantt chart]]> https://projectlibre.com/topic/how-to-change-the-setup-from-week-to-month-in-gantt-chart/#post-3695 Fri, 18 Jul 2025 00:36:07 +0000 Mahalakshmi Balasubramaniam Thank you!

]]>
https://projectlibre.com/topic/how-to-change-the-setup-from-week-to-month-in-gantt-chart/#post-3694 <![CDATA[Reply To: How to change the setup from Week to Month in Gantt chart]]> https://projectlibre.com/topic/how-to-change-the-setup-from-week-to-month-in-gantt-chart/#post-3694 Fri, 18 Jul 2025 00:32:58 +0000 Project_Libre In both the Cloud AI version and the Desktop you can + or – the timescale from hours, Days, 3-days, Week, Month, Quarter and Year. It lets you zoom in and zoom out to see your project.

]]>
https://projectlibre.com/topic/how-to-change-the-setup-from-week-to-month-in-gantt-chart/#post-3404 <![CDATA[How to change the setup from Week to Month in Gantt chart]]> https://projectlibre.com/topic/how-to-change-the-setup-from-week-to-month-in-gantt-chart/#post-3404 Fri, 20 Jun 2025 02:45:51 +0000 Mahalakshmi Balasubramaniam How to change the setup from Week to Month/quarter in Gantt chart so we can see the project timelines in a better view (When using weeks, its so long that we cant see all the activities timelines in a single window without scrolling

]]>
https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3296 <![CDATA[Reply To: Issue Downloading Arabic Manual from Documentation Links]]> https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3296 Thu, 05 Jun 2025 09:10:07 +0000 Project_Libre We will get this updated. The Arabic communnity is a strong focus for the team. Thank you for making us aware!

]]>
https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3295 <![CDATA[Reply To: Issue Downloading Arabic Manual from Documentation Links]]> https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3295 Thu, 05 Jun 2025 09:10:06 +0000 Project_Libre We will get this updated. The Arabic communnity is a strong focus for the team. Thank you for making us aware!

]]>
https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3294 <![CDATA[Reply To: Issue Downloading Arabic Manual from Documentation Links]]> https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3294 Thu, 05 Jun 2025 09:09:56 +0000 Project_Libre We will get this updated. The Arabic communnity is a strong focus for the team. Thank you for making us aware!

]]>
https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3293 <![CDATA[Reply To: Issue Downloading Arabic Manual from Documentation Links]]> https://projectlibre.com/topic/issue-downloading-arabic-manual-from-documentation-links/#post-3293 Thu, 05 Jun 2025 09:09:25 +0000 Project_Libre We will get this updated. The Arabic communnity is a strong focus for the team. Thank you for making us aware!

]]>