predecessor finish to start – Project Libre AI https://projectlibre.com Sun, 09 Nov 2025 16:42:49 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 https://projectlibre.com/wp-content/uploads/2025/08/cropped-CLoud-AI-image-500-x-250-32x32.jpg predecessor finish to start – Project Libre AI https://projectlibre.com 32 32 Start to Finish predecessor connection type not honored https://projectlibre.com/topic/start-to-finish-predecessor-connection-type-not-honored/ Sat, 08 Nov 2025 14:18:52 +0000 https://www.projectlibre.com/topic/start-to-finish-predecessor-connection-type-not-honored/ Hello.

While building a Gantt chart I notice the start date for a task with multiple predecessors with finish to start connection type is not calculated correctly. Task ID 104 has predecessors 38, 63, and 102. Task 63 ends on Nov 28th, but task ID 104 start date is calculated at Nov 13th. Is this a bug or am I missing something?

Thanks

Screenshot here:
https://drive.google.com/file/d/1UeK6RM2qkr9_Uy43UCvXa07DuDSG7s2D/view?usp=sharing”

Predecessor Finish to Start issue

]]>