Summary Tasks – Project Libre AI https://projectlibre.com Wed, 22 Oct 2025 14:34:13 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 https://projectlibre.com/wp-content/uploads/2025/08/cropped-CLoud-AI-image-500-x-250-32x32.jpg Summary Tasks – Project Libre AI https://projectlibre.com 32 32 How can I set a finish date for a summary https://projectlibre.com/topic/how-can-i-set-a-finish-date-for-a-summary/ Wed, 22 Oct 2025 14:34:13 +0000 https://www.projectlibre.com/topic/how-can-i-set-a-finish-date-for-a-summary/ My Gantt chart
For my dissertation project I have to make a gantt chart. The summary line for each phase goes right until the end of the project and I cannot find a way to change it so that for example the phase 2 summary line ends when the phase 3 summary line starts. Its done it for the first one and i have no idea how I have done it.
Any help would be appreciated

]]>